The multi-phased construction schedule calls for placing 19 pre-constructed modules at Concourse D, making the mile-long journey on the same day each week between 1-4 a.m. This method will keep as many gates open as possible during construction.
“We saw a real efficiency in building the modules on a remote site at the airport, while, at the same time, working on the needed foundation and utility relocation works at the concourse,” added Edmund Ramos, vice president project management at WSP and deputy Concourse D project director.
Design started in April 2022 and underground utility enabling work began in November 2023. Work on the modules began in January 2024.
Click here to learn more about the project, and watch the video below for a look at the first module move at Hartsfield-Jackson Airport.